How many arguments does =WORKDAY.INTL have in total?
Explanation: =WORKDAY.INTL has 2 required, 2 optional (4 total).
Question 2 of 10
2/10
What is the fix for #NUM! in =WORKDAY.INTL?
Explanation: If start_date is out of range for the current date base value, WORKDAY.INTL returns the #NUM! error value. If any date in holidays is out of range for the current date base value, WORKDAY.INTL returns the #NUM! error value. If start_date plus day-offset yields an invalid date, WORKDAY.INTL returns the #NUM! error value. — Fix: Use codes 1 to 7 or 11 to 17
Question 3 of 10
3/10
In =WORKDAY.INTL, which is argument #2?
Explanation: Argument #2 is “days”.
Question 4 of 10
4/10
Is argument “start_date” required in =WORKDAY.INTL?
Explanation: “start_date” is required.
Question 5 of 10
5/10
What is the type of argument “holidays” in =WORKDAY.INTL?
Explanation: Type of “holidays” is “Date”.
Question 6 of 10
6/10
Is argument “days” required in =WORKDAY.INTL?
Explanation: “days” is required.
Question 7 of 10
7/10
What is the type of argument “start_date” in =WORKDAY.INTL?
Explanation: Type of “start_date” is “Date”.
Question 8 of 10
8/10
Which is the correct syntax of =WORKDAY.INTL?
Explanation: Correct syntax: =WORKDAY.INTL(start_date, days, [weekend], [holidays])
Question 9 of 10
9/10
What is the type of argument “days” in =WORKDAY.INTL?
Explanation: Type of “days” is “Number”.
Question 10 of 10
10/10
What is the type of argument “weekend” in =WORKDAY.INTL?
Explanation: Type of “weekend” is “Number”.